Contained WithinFind More DocumentationFeatured Support Resources | Download this book in PDF (3221 KB)
Chapter 6 Resource Controls (Overview)After you determine the resource consumption of workloads on your system as described in Chapter 4, Extended Accounting (Overview), you can place boundaries on resource usage. Boundaries prevent workloads from over-consuming resources. The resource controls facility is the constraint mechanism that is used for this purpose. This chapter covers the following topics. For information about how to administer resource controls, see Chapter 7, Administering Resource Controls (Tasks). Resource Controls ConceptsIn the Solaris Operating System, the concept of a per-process resource limit has been extended to the task and project entities described in Chapter 2, Projects and Tasks (Overview). These enhancements are provided by the resource controls (rctls) facility. In addition, allocations that were set through the /etc/system tunables are now automatic or configured through the resource controls mechanism as well. A resource control is identified by the prefix zone, project, task, or process. Resource controls can be observed on a system-wide basis. It is possible to update resource control values on a running system. For a list of the standard resource controls that are available in this release, see Available Resource Controls See Resource Type Properties for information on available zone-wide resource controls. Resource Limits and Resource ControlsUNIX systems have traditionally provided a resource limit facility (rlimit). The rlimit facility allows administrators to set one or more numerical limits on the amount of resources a process can consume. These limits include per-process CPU time used, per-process core file size, and per-process maximum heap size. Heap size is the amount of scratch memory that is allocated for the process data segment. The resource controls facility provides compatibility interfaces for the resource limits facility. Existing applications that use resource limits continue to run unchanged. These applications can be observed in the same way as applications that are modified to take advantage of the resource controls facility. Interprocess Communication and Resource ControlsProcesses can communicate with each other by using one of several types of interprocess communication (IPC). IPC allows information transfer or synchronization to occur between processes. Prior to the Solaris 10 release, IPC tunable parameters were set by adding an entry to the /etc/system file. The resource controls facility now provides resource controls that define the behavior of the kernel's IPC facilities. These resource controls replace the /etc/system tunables. Obsolete parameters might be included in the /etc/system file on this Solaris system. If so, the parameters are used to initialize the default resource control values as in previous Solaris releases. However, using the obsolete parameters is not recommended. To observe which IPC objects are contributing to a project's usage, use the ipcs command with the -J option. See How to Use ipcs to view an example display. For more information about the ipcs command, see ipcs(1). For information about Solaris system tuning, see the Solaris Tunable Parameters Reference Manual. Resource Control Constraint MechanismsResource controls provide a mechanism for the constraint of system resources. Processes, tasks, projects, and zones can be prevented from consuming amounts of specified system resources. This mechanism leads to a more manageable system by preventing over-consumption of resources. Constraint mechanisms can be used to support capacity-planning processes. An encountered constraint can provide information about application resource needs without necessarily denying the resource to the application. Project Attribute MechanismsResource controls can also serve as a simple attribute mechanism for resource management facilities. For example, the number of CPU shares made available to a project in the fair share scheduler (FSS) scheduling class is defined by the project.cpu-shares resource control. Because the project is assigned a fixed number of shares by the control, the various actions associated with exceeding a control are not relevant. In this context, the current value for the project.cpu-shares control is considered an attribute on the specified project. Another type of project attribute is used to regulate the resource consumption of physical memory by collections of processes attached to a project. These attributes have the prefix rcap, for example, rcap.max-rss. Like a resource control, this type of attribute is configured in the project database. However, while resource controls are synchronously enforced by the kernel, resource caps are asynchronously enforced at the user level by the resource cap enforcement daemon, rcapd. For information on rcapd, see Chapter 10, Physical Memory Control Using the Resource Capping Daemon (Overview) and rcapd(1M). The project.pool attribute is used to specify a pool binding for a project. For more information on resource pools, see Chapter 12, Resource Pools (Overview). Configuring Resource Controls and AttributesThe resource controls facility is configured through the project database. See Chapter 2, Projects and Tasks (Overview). Resource controls and other attributes are set in the final field of the project database entry. The values associated with each resource control are enclosed in parentheses, and appear as plain text separated by commas. The values in parentheses constitute an “action clause.” Each action clause is composed of a privilege level, a threshold value, and an action that is associated with the particular threshold. Each resource control can have multiple action clauses, which are also separated by commas. The following entry defines a per-task lightweight process limit and a per-process maximum CPU time limit on a project entity. The process.max-cpu-time would send a process a SIGTERM after the process ran for 1 hour, and a SIGKILL if the process continued to run for a total of 1 hour and 1 minute. See Table 6–3.
Note – On systems that have zones enabled, zone-wide resource controls are specified in the zone configuration using a slightly different format. See Zone Configuration Data for more information. The rctladm command allows you to make runtime interrogations of and modifications to the resource controls facility, with global scope. The prctl command allows you to make runtime interrogations of and modifications to the resource controls facility, with local scope. For more information, see Global and Local Actions on Resource Control Values, rctladm(1M) and prctl(1). Note – On a system with zones installed, you cannot use rctladm in a non-global zone to modify settings. You can use rctladm in a non-global zone to view the global logging state of each resource control. Available Resource ControlsA list of the standard resource controls that are available in this release is shown in the following table. The table describes the resource that is constrained by each control. The table also identifies the default units that are used by the project database for that resource. The default units are of two types:
Thus, project.cpu-shares specifies the number of shares to which the project is entitled. process.max-file-descriptor specifies the highest file number that can be assigned to a process by the open(2) system call. Table 6–1 Standard Project, Task, and Process Resource Controls
You can display the default values for resource controls on a system that does not have any resource controls set or changed. Such a system contains no non-default entries in /etc/system or the project database. To display values, use the prctl command. Zone-Wide Resource ControlsZone-wide resource controls limit the total resource usage of all process entities within a zone. Zone-wide resource controls can also be set using global property names as described in Setting Zone-Wide Resource Controls and How to Configure the Zone. Table 6–2 Zones Resource Controls
For information on configuring zone-wide resource controls, see Resource Type Properties and How to Configure the Zone. To use zone-wide resource controls in lx branded zones, see How to Configure, Verify, and Commit the lx Branded Zone. Note that it is possible to apply a zone-wide resource control to the global zone. See Using the Fair Share Scheduler on a Solaris System With Zones Installed for additional information. Units SupportGlobal flags that identify resource control types are defined for all resource controls. The flags are used by the system to communicate basic type information to applications such as the prctl command. Applications use the information to determine the following:
The following global flags are available:
Scaled values can be used with resource controls. The following example shows a scaled threshold value: task.max-lwps=(priv,1K,deny) Note – Unit modifiers are accepted by the prctl, projadd, and projmod commands. You cannot use unit modifiers in the project database itself. Resource Control Values and Privilege LevelsA threshold value on a resource control constitutes an enforcement point where local actions can be triggered or global actions, such as logging, can occur. Each threshold value on a resource control must be associated with a privilege level. The privilege level must be one of the following three types.
A resource control is guaranteed to have one system value, which is defined by the system, or resource provider. The system value represents how much of the resource the current implementation of the operating system is capable of providing. Any number of privileged values can be defined, and only one basic value is allowed. Operations that are performed without specifying a privilege value are assigned a basic privilege by default. The privilege level for a resource control value is defined in the privilege field of the resource control block as RCTL_BASIC, RCTL_PRIVILEGED, or RCTL_SYSTEM. See setrctl(2) for more information. You can use the prctl command to modify values that are associated with basic and privileged levels. Global and Local Actions on Resource Control ValuesThere are two categories of actions on resource control values: global and local. Global Actions on Resource Control ValuesGlobal actions apply to resource control values for every resource control on the system. You can use the rctladm command described in the rctladm(1M) man page to perform the following actions:
You can disable or enable the global logging action on resource controls. You can set the syslog action to a specific degree by assigning a severity level, syslog=level. The possible settings for level are as follows:
By default, there is no global logging of resource control violations. The level n/a indicates resource controls on which no global action can be configured. Local Actions on Resource Control ValuesLocal actions are taken on a process that attempts to exceed the control value. For each threshold value that is placed on a resource control, you can associate one or more actions. There are three types of local actions: none, deny, and signal=. These three actions are used as follows:
Not all of the actions can be applied to every resource control. For example, a process cannot exceed the number of CPU shares assigned to the project of which it is a member. Therefore, a deny action is not allowed on the project.cpu-shares resource control. Due to implementation restrictions, the global properties of each control can restrict the range of available actions that can be set on the threshold value. (See the rctladm(1M) man page.) A list of available signal actions is presented in the following table. For additional information about signals, see the signal(3HEAD) man page. Table 6–3 Signals Available to Resource Control Values
Resource Control Flags and PropertiesEach resource control on the system has a certain set of associated properties. This set of properties is defined as a set of flags, which are associated with all controlled instances of that resource. Global flags cannot be modified, but the flags can be retrieved by using either rctladm or the getrctl system call. Local flags define the default behavior and configuration for a specific threshold value of that resource control on a specific process or process collective. The local flags for one threshold value do not affect the behavior of other defined threshold values for the same resource control. However, the global flags affect the behavior for every value associated with a particular control. Local flags can be modified, within the constraints supplied by their corresponding global flags, by the prctl command or the setrctl system call. See setrctl(2). For the complete list of local flags, global flags, and their definitions, see rctlblk_set_value(3C). To determine system behavior when a threshold value for a particular resource control is reached, use rctladm to display the global flags for the resource control . For example, to display the values for process.max-cpu-time, type the following:
The global flags indicate the following.
Use the prctl command to display local values and actions for the resource control.
The max (RCTL_LOCAL_MAXIMAL) flag is set for both threshold values, and the inf (RCTL_GLOBAL_INFINITE) flag is defined for this resource control. An inf value has an infinite quantity. The value is never enforced. Hence, as configured, both threshold quantities represent infinite values that are never exceeded. Resource Control EnforcementMore than one resource control can exist on a resource. A resource control can exist at each containment level in the process model. If resource controls are active on the same resource at different container levels, the smallest container's control is enforced first. Thus, action is taken on process.max-cpu-time before task.max-cpu-time if both controls are encountered simultaneously. Figure 6–1 Process Collectives, Container Relationships, and Their Resource Control Sets
Global Monitoring of Resource Control EventsOften, the resource consumption of processes is unknown. To get more information, try using the global resource control actions that are available with the rctladm command. Use rctladm to establish a syslog action on a resource control. Then, if any entity managed by that resource control encounters a threshold value, a system message is logged at the configured logging level. See Chapter 7, Administering Resource Controls (Tasks) and the rctladm(1M) man page for more information. Applying Resource ControlsEach resource control listed in Table 6–1 can be assigned to a project at login or when newtask, su, or the other project-aware launchers at, batch, or cron are invoked. Each command that is initiated is launched in a separate task with the invoking user's default project. See the man pages login(1), newtask(1), at(1), cron(1M), and su(1M) for more information. Updates to entries in the project database, whether to the /etc/project file or to a representation of the database in a network name service, are not applied to currently active projects. The updates are applied when a new task joins the project through login or newtask. Temporarily Updating Resource Control Values on a Running SystemValues changed in the project database only become effective for new tasks that are started in a project. However, you can use the rctladm and prctl commands to update resource controls on a running system. Updating Logging StatusThe rctladm command affects the global logging state of each resource control on a system-wide basis. This command can be used to view the global state and to set up the level of syslog logging when controls are exceeded. Updating Resource ControlsYou can view and temporarily alter resource control values and actions on a per-process, per-task, or per-project basis by using the prctl command. A project, task, or process ID is given as input, and the command operates on the resource control at the level where the control is defined. Any modifications to values and actions take effect immediately. However, these modifications apply to the current process, task, or project only. The changes are not recorded in the project database. If the system is restarted, the modifications are lost. Permanent changes to resource controls must be made in the project database. All resource control settings that can be modified in the project database can also be modified with the prctl command. Both basic and privileged values can be added or be deleted. Their actions can also be modified. By default, the basic type is assumed for all set operations, but processes and users with superuser privileges can also modify privileged resource controls. System resource controls cannot be altered. Commands Used With Resource ControlsThe commands that are used with resource controls are shown in the following table.
The resource_controls(5) man page describes resource controls available through the project database, including units and scaling factors. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||